D0701040 Opinion Granting a Certificate of Public Convenience and Necessity
Word Document PDF Document

No local discretionary (e.g., use) permits are required, since the CPUC has preemptive jurisdiction over the construction, maintenance, and operation of SCE facilities in California. SCE would still have to obtain all ministerial building and encroachment permits from local jurisdictions, and the CPUC's General Order 131-D requires that, in locating electric facilities such as DPV2, SCE consult with local agencies regarding land use matters. The CPUC's authority does not preempt special districts, such as the South Coast Air Quality Management District, or other State agencies or the federal government.

Resource

Impact Evaluation Category

Rationale for No Impact or Less than Significant Impacts

Biological Resources

Impact B-3: Construction activities will create dust that may result in degradation to vegetation

SCE will implement dewatering measures (Air Quality) to decrease fugitive dust including reduced vehicle speeds, use of tackifiers, and periodic watering of the ROW.

 

Impact B-4: Construction activities and increased vehicular traffic on access roads will result in disturbance to wildlife species

Local wildlife populations along the ROW will temporarily decline or disperse during the construction phase of the project but will return to their pre-construction levels following the restoration of the laydown areas and tower erection sites. Also, as construction is limited to relatively small areas wildlife will return to the ROW as work crews move to new tower locations.

 

Impact B-7: Construction activities will result in indirect or direct loss of listed wildlife or habitat

Invertebrates. There is no indication that any rare or listed invertebrates occur within the Project area.

Amphibians. No listed amphibians are located within the habitat conditions of the Project route, or known recorded occurrences of these species do occur in or adjacent to the construction area.

 

Impact B-8: Construction activities will result in indirect or direct loss of individuals, or a direct loss of habitat for sensitive plants

The Arizona segments of the Project contain plant species protected under the Arizona Native Plant Law. However, this portion of the Project does not contain suitable habitat for sensitive plants and is located outside the geographical range for any of the sensitive plant species These species have not been previously recorded in the Project area and were not identified during surveys conducted by SCE.

 

Impact B-9: Construction activities will result in indirect or direct loss of individuals, or a direct loss of habitat for sensitive wildlife

Invertebrates. Sensitive invertebrate species were not observed along the Project route; however, the Cheese-weed moth lacewing has a moderate potential to occur in the Arizona segments. Although suitable habitat for the cheese-weed moth lacewing occurs along the project route, known locations of the species are more than 60 miles south of the Project. Consequently, implementation of the APMs B-1, B-3, B-8, B-10, B-12, B-13, B-14, B-16, and B-23 and avoidance of known locations of cheese-weed moth lacewing makes impacts to this species unlikely.

Amphibians. There is no indication that any sensitive amphibians occur along the Project route. Surveys conducted of the project area did not detect the presence of sensitive amphibian species and impacts are considered less than significant.

 

Impact B-12: Construction activities will result in adverse effects to linkages and wildlife movement corridors

The disturbance associated with project construction will result in temporary impacts to wildlife utilizing the waterways and adjacent habitat as a movement corridor. A temporary increase in traffic and activities in these areas will not impede the movement of wildlife and will not affect the nocturnal movement of wildlife.

 

Impact B-13: Construction activities may conflict with local policies or ordinances protecting biological resources

The Project will traverse the jurisdictions of the BLM and Riverside and San Bernardino Counties. Plans developed by these jurisdictions were reviewed to determine if there were any biological resources policies that will apply to the construction and operation of the Project. The Project was found to be applicable to many identified policies as evaluated in Section D.2.6.1.11 of the EIR/EIS. See Appendix 2 of the Draft EIR/EIS for a complete discussion of applicable biological resources policies

 

Impact B-14: Operation of the transmission line may result in electrocution of listed and/or protected bird species

Peregrine falcons, golden eagles, and other large aerial perching birds are most susceptible to electrocution because of their size, distribution, and behavior. In addition, raptor species that utilize the towers for nesting could be electrocuted while landing. Based on studies completed, it was found that the likelihood of electrocutions occurring at voltages greater than 69 kV is extremely low.

 

Impact B-17: Wildlife mortality resulting from traffic on access roads

The operations and maintenance activities will be conducted at about the same frequency as currently exists for the DPV1 transmission line. Vehicle speeds will be limited to a maximum of 25 mph in desert tortoise habitat (APM B-29). The implementation of this APM, and the approximate same level of use of the roads as currently exists for operation and maintenance activities, will result in a similar impact to what currently exists.

Biological Resources, cont.

Impact B-18: The Project will result in disturbance to Management Indicator Species (MIS)

Healthy Diverse Habitats (mule deer). To reduce potential impacts, construction vehicles will remain on established roads except for tower construction in order to avoid unnecessary disturbances to wildlife (see APM B-3), and vehicles will be required to drive at low speeds on NFS lands (see APM A-5). Although construction may result in temporary disturbance to this species, the impact is considered adverse but not significant.

Fragmentation (mountain lion). Construction of Devers-Valley No. 2 will result in some loss of habitat as a result of tower footings, access roads, and construction staging areas. However, much of this will be temporary and only a small percentage of regional habitat will be permanently removed at each tower location. In addition, Devers-Valley No. 2 will not create a physical barrier to dispersal or limit the connectivity between core habitat areas. Although construction may result in temporary impacts to mountain lions, impacts are considered adverse but not significant.

Montane Conifer Forest (California spotted owl, California black oak, and white fir). Conifer stand and oak woodlands utilized by this species will not be impacted by the Devers-Valley No. 2 Alternative. White fir and black oak are not present in the corridor for Devers-Valley No. 2. Impacts to these MIS will not occur.

Aquatic Habitat (Arroyo toad). The arroyo toad is not expected to occur on the designated utility corridor on NFS lands. This species may be present at Whitewater Canyon which is on non-NFS lands. This species will not be affected by Devers-Valley No. 2. Impacts to this MIS will not occur.

Oak Regeneration (Blue oak, Engleman oak, and Valley oak). Blue oak, valley oak, and Engleman oaks were not identified in the Project utility corridor and will not be impacted by project construction. Impacts to these MIS will not occur.

Bigcone Douglas-fir Forest (Bigcone Douglas-fir). This MIS is not present in the designated utility corridor for the Devers-Valley No. 2 Alternative. Impacts to this MIS will not occur.

Coulter Pine Forest (Coulter pine). Coulter pine is a major component of lower montane forests which are not present in the designated utility corridor for Devers-Valley No. 2. Impacts to this MIS will not occur.

 

Cumulative Impacts

Several transmission projects are being constructed or proposed within the same utility corridor. The Project will remain primarily within an existing transmission line ROW and will result in minimal permanent impacts to biological resources. Temporarily impacted areas will be restored to pre-existing conditions. Although the Project will accommodate the other transmission and energy projects that will in turn enable future growth and development in the region, the Project will not significantly contribute to cumulative effects of these projects on biological resources.

Visual Resources

V-1 Short-term visibility of construction activities, equipment, and night lighting

Impacts result from visibility of equipment, vehicles, materials and work force; construction and night lighting will be temporary. APMs B-5, B-14, L-1 and L-9 as well as Mitigation Measures V-1a and V-1b will further reduce effects from this less than significant impact.

 

V-3 Increased structure contrast when viewed from Key Viewpoint 1, south of the Big Horn Mountains

Low level of change at this viewpoint (I-10; west of Burnt Mountains). New structures/conductors visible but not prominent. APMs V-1 thru V-3, V-5 thru V-10, L-4, and L-5 as well as Mitigation Measure V-3a will further reduce effects from this less than significant impact.

 

V-4: Increased structure contrast, view blockage, and skylining when viewed from Key Viewpoint 2 on Interstate 10, crossing the Harquahala Plain

Project will be similar in scale and design to the DPV1 line and conductor spans will generally be matched. Mitigation Measure V-3a will further reduce less than significant impacts.

Visual Resources, cont.

V 5: Increased structure contrast, view blockage, and skylining when viewed from Key Viewpoint 3 at the north end of the Eagletail Mountains (VRM)

Line/Tower will repeat the characteristics of the existing capacitor bank and will not dominate the view of the casual observer. Mitigation Measure V-3a will further reduce less than significant impacts.

V 6: Increased structure contrast, industrial character, and skylining when viewing the Arizona Series Capacitor Bank from Pipeline Road (VRM)

New capacitor bank will repeat the characteristics of the existing capacitor bank and will not dominate the view of the casual observer. Mitigation Measures V-6a and V-6c will further reduce less than significant impacts

V 8: Increased structure contrast, view blockage, and skylining when viewed from Key Viewpoint 5 on U.S. 95 near the Crystal Hill Road Entrance to Kofa NWR

Line/Tower will repeat the characteristics of the existing line and will not dominate the view of the casual observer. Mitigation Measure V-3a will further reduce less than significant impacts.

V 9: Increased structure contrast, industrial character, and view blockage when viewed from Key Viewpoint 6 on Pipeline Road near Copper Bottom Pass

Line/Tower will repeat the characteristics of the existing line and will not dominate the view of the casual observer. Mitigation Measure V-3a will further reduce less than significant impacts.

V 10: Increased structure contrast, view blockage, and skylining when viewed from Key Viewpoint 7 on the Colorado River

Line/Tower will repeat the characteristics of the existing line and will not dominate the view of the casual observer. Mitigation Measure V-3a will further reduce less than significant impacts.

V 11: Increased structure contrast, view blockage, and skylining when viewed from Key Viewpoint 8 on SR 78 Near Ripley

The Project will be similar in scale and design to the DPV1 line and conductor spans will generally be matched. Mitigation Measure V-3a will further reduce less than significant impacts.

V 12: Introduction of new structure contrast and industrial character when viewing the Blythe Optical Repeater Station site from nearby local roads

The facility will appear subordinate to other landscape features including the existing and Project transmission line structures. Mitigation Measures V-6a and V-6c will further reduce less than significant impacts.

 

V 13: Increased structure contrast, industrial character, view blockage, and skylining when viewing the Midpoint Substation site from the nearby BLM access road

Substation will repeat the characteristics of the existing line and will not dominate the view of the casual observer. Mitigation Measures V-6a and V-6c will further reduce less than significant impacts.

Visual Resources, cont.

V 14: Increased structure contrast, view blockage, and skylining when viewed from Key Viewpoint 9 on Interstate 10 in the eastern Chuckwalla Valley

The Project will be similar in scale and design to the DPV1 line and conductor spans will generally be matched. Mitigation Measure V-3a will further reduce less than significant impacts.

V 16: Increased structure contrast, view blockage, and skylining when viewing the Orocopia Mountains from Key Viewpoint 11 on Interstate 10

Line/Tower will repeat the characteristics of the existing line and will not dominate the view of the casual observer. Mitigation Measure V-3a will further reduce less than significant impacts.

V-17: Increased structure contrast, industrial character, and skylining when viewing the proposed California Series Capacitor Bank from Interstate 10 or Red Cloud Road

New capacitor bank will repeat the characteristics of the existing capacitor bank and will not dominate the view of the casual observer. Mitigation Measures V-6a and V-6c will further reduce less than significant impacts

V-18: Increased structure contrast and view blockage when viewing the Orocopia Mountains from Key Viewpoint 12 on Cottonwood Springs Road when exiting Joshua Tree National Park

Line/Tower will repeat the characteristics of the existing line and will not dominate the view of the casual observer. Mitigation Measure V-3a will further reduce less than significant impacts.

V-19: Increased structure contrast, industrial character, and view blockage when viewed from Key Viewpoint 13 in the Terra Lago golf and residential development in Indio

Project will be similar in scale and design to the DPV1 line and conductor spans will generally be matched. Mitigation Measure V-3a will further reduce less than significant impacts.

 

V-20: Increased structure contrast, industrial character, and view blockage when viewing the Santa Rosa Mountains to the south from Key Viewpoint 14 in the Coachella Valley Preserve, just west of Thousand Palms Canyon Road

Line/Tower will repeat the characteristics of the existing line and will not dominate the view of the casual observer. Mitigation Measure V-3a will further reduce less than significant impacts.

Land Use

L-1 Construction will temporarily disturb the land uses it traverses or adjacent land uses.

Construction in remote areas will not disturb existing land uses such as at the Harquahala Switchyard and the location of the substations.

L-2 Operation will result in permanent preclusion of land uses it traverses or adjacent land uses

Operation of the project in areas where the transmission line will be within an existing corridor or adjacent to existing towers will not permanently preclude land uses.

Wilderness & Recreation

WR 1: Construction of the Proposed Project would temporarily reduce access and visitation to recreation or wilderness areas

Construction activities will not directly impact a wilderness or recreational resource. Within segments of the route where there are no wilderness and recreation areas, this impact has been deemed no impact.

WR-2: Operation would change the character of a recreation or wilderness area, diminishing its recreational value

Operation of Project will not change the character of recreational activities along the Cactus City Rest Area to Devers Substation segment and North of Alligator Rock. The location of the Project will be adjacent to existing utility structures.

Within segments of the route where there are no wilderness and recreation areas, this impact has been deemed no impact.

WR-3: Operation would permanently preclude recreational activities.

Operation of Project will not permanently preclude existing recreational activities along the Harquahala to Kofa NWR segment. The location of the Project will be adjacent to existing utility structures.

Within segments of the route where there are no wilderness and recreation areas, this impact has been deemed no impact.

Agriculture

AG-6 Operation will conflict with a Williamson Act contract

Permanent disturbance caused by the Project will not exceed the 10-acre threshold set to determine significance. APM L-5 will minimize conflicts with Williamson Act land.

Cultural Resources

C-1 Construction of the project will cause an adverse change to known historic properties

If known sites are avoided, no impacts to identified and known historic properties will occur as a result of construction disturbances

C-2 Construction of the project could cause an adverse change to unknown significant buried prehistoric and historical archaeological sites or buried Native American human remains

No impacts to buried prehistoric and historical sites, or buried human remains will occur if none of these resources are not encountered or discovered during the Project's ground disturbing construction activities

Noise

N-2: Permanent noise levels along the ROW will increase due to corona noise from operation of the transmission lines

Worst-case wet weather and heavy load conditions will not normally occur continuously during a 24-hour period, but if they do, modeling results provided by SCE in a late-filed exhibit (August 1, 2006) show that the corona noise caused by the Project will be below 65 Ldn at all times for any location greater than 25 feet from the edge of the Devers-Harquahala ROW within the following segments and alternatives, resulting in less than significant impacts:

· Harquahala to Kofa National Wildlife Refuge

· Kofa National Wildlife Refuge

· Kofa National Wildlife Refuge to Colorado River

· Midpoint Substation to Cactus City Rest Area

· Harquahala Switchyard Alternative

· SCE and DSW Substations Alternative

Noise, cont.

N-3: Maintenance activities during transmission line operation will increase ambient noise levels

Maintenance visits will be infrequent and will not involve heavy-duty equipment, no notable noise increase will occur as a result of this activity, and the noise impact will be less than significant for all locations along the transmission line ROW.

N-4: Operation of modified and new substations will result in increased ambient noise levels

The noise levels surrounding the Substation sites will likely be close to 60 dBA near the substation fence. Because of the relatively low level noise sources and the lack of sensitive receptors near the Substation sites, the operational noise impact will be less than significant.

Transportation and Traffic

T-1: A roadway could be temporarily closed to through traffic due to project construction

Prior to conducting work within or above a road ROW, an encroachment permit or similar authorization will be required by the applicable jurisdictional agency at locations where the construction activities will occur within or above the public road ROW. Compliance with the encroachment permits will ensure that potential impacts associated with short-term road closures are less than significant.

T-2: Temporary road closures due to construction will disrupt the operation of emergency service providers

In the event that an emergency service provider vehicle were to approach a roadway temporarily blocked by overhead construction activities, SCE will be able to accommodate the emergency service provider vehicle by immediately stopping work to allow the passage of the emergency vehicle with minimal delay. Impacts will be less than significant.

T-3: Construction will cause temporary road and lane closures that will temporarily disrupt bus transit services

Potential closure of freeways or roadways along the Project route will be a one time occurrence that will only last for a few minutes during the early morning before dawn. Therefore, temporary stringing activities will not substantially disrupt Greyhound or local public bus operations. Impacts related to disruptions to bus transit services will be less than significant.

T-4: Construction activities will cause temporary road closures that will impede pedestrian and/or bicycle movements

In the event pedestrian or bicycle movement was temporarily blocked during construction, roadways will likely be blocked for only a few minutes. In addition, pedestrians and bicyclists will likely be able to take short detours around blocked roads and construction areas. Impacts will be less than significant.

T-5: Construction will generate additional traffic on the regional and local roadways

Pursuant to the requirements of APM A-7, workers will drive or ride in project vehicles to work areas along the transmission line ROWs. As the transmission line workers will be dispersed throughout the project area and will not typically be working at the same place at any one time, only minimal traffic increases will occur on the study area roadway network relative to construction workers. Similarly, the construction-related truck traffic will be dispersed throughout the project route and throughout the workday. Project-related construction traffic will result in a less than significant impact on traffic conditions in the project area.

 

T-6: Construction will conflict with planned transportation projects

The public agencies that have jurisdiction over the affected roadways have been notified of the project through the Notice of Preparation/Notice of Intent, and an encroachment permit or other such agreement must be obtained for each location where the project will interface with a roadway or other transportation facility. Complying with local permits and agreements will ensure appropriate coordination between SCE and the affected agencies so that conflicts will be avoided or minimized. The impacts will be less than significant.

 

T-8: Operation will generate additional traffic on the regional and local roadways

Operation of the transmission line will have negligible impacts on the ground transportation system (roadways and railroads) under normal circumstances, as the inspection and maintenance activities will generate only a very small volume of vehicular traffic. Project-related operational traffic will result in a less than significant impact on traffic conditions in the project area.

Transportation and Traffic, cont.

T-9: Construction activities will cause a temporary disruption to rail traffic or operations

The Project will cross the Burlington Northern Santa Fe railroad tracks near Lovekin Boulevard at MP E105. Transmission line stringing activities over the railroad could temporarily affect rail operations. SCE will comply with the regulations and procedures of Burlington Northern Santa Fe relative to disruption to rail service or safety within the railroad ROW. Through compliance with the railroad company requirements, the impacts of the Project on rail traffic and operations will be less than significant.

 

T-10: Construction activities will affect aviation activities associated with public airports

The presence of large cranes that will be required to install the new towers could affect aviation activities associated with the Desert Center Airport, Chiriaco Summit Airport, Banning Airport, San Bernardino International Airport, Blythe Airport, and various heliports. However, pursuant to FAA guidelines, SCE will submit FAA Form 7460 1, Notice of Proposed Construction or Alteration, to the Manager of the FAA Air Traffic Division for review and approval of the project. Adherence to FAA guidelines will insure that construction impacts to aviation activities will be less than significant.

T-11: Operations will affect aviation activities associated with public airports

The presence of new towers could affect aviation activities associated with the Desert Center Airport, Chiriaco Summit Airport, Banning Airport, San Bernardino International Airport, Blythe Airport, and various heliports. However, pursuant to FAA guidelines, SCE will submit FAA Form 7460 1, Notice of Proposed Construction or Alteration, to the Manager of the FAA Air Traffic Division for review and approval of the project. Adherence to FAA guidelines will insure that construction impacts to aviation activities will be less than significant.

T-13: Helicopter use during construction could conflict with rescue helicopter use within the Kofa National Wildlife Refuge

Because of the remote nature of the Kofa NWR, helicopters are sometimes used for rescue operations. This situation is not expected to occur frequently, and the impact is less than significant. However, in order to ensure that these rescue flights do not conflict with SCE's construction helicopter operations, Mitigation Measure T-13a will be implemented

T-14: Construction use of roads could result in increased public use of unauthorized roads with the Kofa National Wildlife Refuge

The utility road at the west Refuge boundary (Highway 95) to approximately Milepost 79.5 (where the utility road joins Crystal Hill Road) is not a public access road. The public may see construction vehicles using this road and think that it is available for public use. Public use of this road will result in an adverse, but less than significant. However, in order to prevent public use of this road, Mitigation Measure T-14a will be implemented.

Cumulative Traffic Impacts

None of the traffic impacts associated with the Project have the potential to combine with the impacts of other projects to create a cumulatively considerable traffic impact. Those impacts from other projects that have the potential to combine cumulatively with impacts from the Project will be in the use of roads for delivery of labor and materials. However, in undeveloped areas traffic volumes are low, so this will not create a significant impact. In urban and urbanizing areas, the volume of traffic associated with the projects is not sufficiently large to create a cumulatively considerable impact.

Public Health and Safety

PS-3 Effects on Cardiac Pacemakers

While the transmission line's electric field may impact operation of some older model pacemakers, the result of the interference is of short duration and will not be significant or harmful

PS-4 Wind, Earthquake, and Fire Hazards

SCE is required to design the transmission line in accordance with safety requirements of the CPUC's G.O. 95 and other applicable requirements, so safety impacts associated with wind, earthquake and fire will not be significant.

PS-5 Transmission Lines in Agricultural Areas Present a Safety Hazard to Aerial Applicators

Pilots are now aware of the presence of the DPV1 transmission line, which has been in place since 1982. However, pilots may have no knowledge that new transmission lines and towers may have been constructed, which creates an increased danger. While this will be an adverse, but less than significant impact, Mitigation Measures A-1a and A-4a will further reduce the impact.

Public Health and Safety, cont.

PS-5 Transmission Lines in Agricultural Areas Present a Safety Hazard to Aerial Applicators

Although most facilities of this type may received power from the SCE grid supplied by DPV2, the facilities will also have back up power/generators to prevent electricity interruptions in the event of an outage, such as will occur with a terrorist attack on a transmission line.

Air Quality

AQ-1: Construction will generate dust and exhaust emissions

The level of construction activity within Maricopa County Air Quality Department (MCAQD) district will be relatively minor resulting in emissions well below the applicable thresholds. Additionally, the earthmoving permits required by the MCAQD will require Best Available Control Measures (BACM) for construction dust control, which will assure that dust emissions will be controlled sufficiently to remain below the significance threshold. The regional emission impact for MCAQD is less than significant.

AQ-2: Operation, maintenance, and inspections will generate dust and exhaust emissions

The emissions caused directly by operation, maintenance, and inspection of the Project will be below all applicable regional daily and annual emission thresholds. The emissions show that the Project will not result in significant direct operational emissions within any jurisdiction. Therefore, the operational impacts of the Project will not conflict with any air quality management plan, and the project's direct operations will have a less than significant impact.

AQ-3: Power generated during transmission line operation will cause emissions from power plants

The precise location and quantity of operational transmission line emissions will likely change over time depending on the ultimate sources of power flowing into DPV2. Any NOx emissions represent a small change when considered in a statewide context. The increase in power plant emissions along the Project route, therefore, is considered to be an adverse but less than-significant-impact.

Hydrology and Water Quality

H-1 Construction activity could degrade water quality due to erosion and sedimentation

With the implementation of APMs W-1 through W-3, and W-7 through W-9 and the required SWPPP, construction-related water quality degradation from soil erosion and sedimentation will not be significant.

H-3 Increased runoff from new impervious areas resulting in flooding or increased erosion downstream

As the amount of new impervious area created by the Project will be generally small, it will only result in small increases in runoff that are not likely to have an appreciable impact. Implementation of APM W-8 will ensure that the adverse affects associated with increased runoff from new impervious areas will be less than significant

H-5 Excavation could degrade groundwater quality

Discharge of spilled pollutants into excavated areas will be minimized by the hazardous material plans required pursuant to APMs W-3.

Cumulative Hydrology and Water Resources Impacts

Overall, the Project's impacts on hydrology and water resources were found to be less than significant with mitigation incorporated. In addition, the contribution of the Project to the cumulative increase in flood discharges, flood flows, impacts to groundwater supplies, degradation of water quality, will be negligible.

Geology, Soils, and Mineral Resources

G-1 Construction could accelerate erosion

In the Palo Verde Valley and Midpoint Substation segments and in the segments west of Banning, excavation and grading for tower foundations, work areas, access roads, and spur roads could loosen soil and accelerate erosion. However, because the soil associations identified along the segment are not known to contain desert pavement, implementation of APMs W-3, W-7 through W-9, W-11, G-10 through G-14, and G-19 will ensure that potential impacts will be less than significant

G-5 Project structures could be damaged by seismically included groundshaking and ground failure

At Midpoint Substation, there will be no impacts associated with seismically induced ground failure or groundshaking. In the segments west of the Midpoint Substation, it is likely that the transmission line towers will be subjected to at least one moderate or larger earthquake occurring close enough to produce groundshaking along this segment. However, implementation of APMs G-4 and G-17 will ensure that impacts related to seismically included groundshaking are less than significant

Geology, Soils, and Mineral Resources, cont.

Cumulative Geologic Impacts

Cumulative impacts consist of the loss of unique geologic features or known mineral and/or energy resources, or the triggering or acceleration of erosion or slope failures. Because other identified projects in the project area will need to comply with erosion control requirements, the effects of these projects in conjunction with Project on the geologic environment are not cumulatively considerable.

Socioeconomics

S-1: Accidents during project construction will disrupt utility systems

As required by Arizona State Underground Facilities Law or, simply, the Blue Stake Law, (ARS Chapter 2, Article 6.3, Sections 40-360.21 through 40-360.32.), SCE will contact a regional notification center at least two days prior to any excavation, trenching, or other digging activities. In addition, according to Section 1, Chapter 3.1, "Protection of Underground Infrastructure," Article 2 of California Government Code 4216-4216.9, SCE will contact a regional notification center at least two days prior to excavation of any subsurface installation. The application of these required activities, impacts related to a collocation or utility disruption will be less than significant.

S-2: Project construction will place demands on local water or solid waste utilities

Water used during Project construction and operation is not anticipated to place demands on the available water suppliers serving the route resulting and requiring the need for new or expanded water facilities. Consequently, water demands of the Project will have a less than significant impact.

The volume of waste generated by Project construction and operation will be very small compared to the capacities of the landfills serving the route. These landfills will have adequate capacity to receive solid waste generated during construction and operation of the Project. Less than significant impacts to solid waste facilities will occur.

S-3: Project operation will provide revenue to the Agua Caliente Band of Cahuilla Indians

The Project will traverse allottee lands under the jurisdiction of the Agua Caliente Band of Cahuilla Indians. If it is determined that a CUP is not necessary, any compensation provided to the Agua Caliente Band of Cahuilla Indians as a part of negotiations over the land will also provide revenue for the Agua Caliente. Revenue generation will be considered a beneficial impact to the Tribe. Therefore, under the Project, payments made by SCE to the Agua Caliente Band of Cahuilla Indians in the form of fees or compensation will provide a beneficial socioeconomic impact

Cumulative Socioeconomics Impacts

The siting of the Project in addition to the other transmission projects will not significantly increase the potential for a collocation accident or a disruption to the utility system. As the Project will adhere to California Government Code 4216-4216.9 and the Arizona State Underground Facilities Law, the Project will not have a significant incremental contribution to potential utility disruptions.

Cumulative project construction could place demands on local water or solid waste services. However, local planning agencies augment or develop water, wastewater and solid waste facilities to meet the anticipated needs of population projected for the region. Therefore, the current cumulative impact of all development projects within the cumulative area of impact on water and solid waste facilities serving the areas is less than significant because the impacts of growth have already been anticipated and accommodated in approved plans.

C-1d Conduct data recovery to reduce adverse effects. If National Register of Historic Places (NRHP)-eligible resources, as determined by the BLM and SHPO, cannot be protected from direct impacts of the Project, data-recovery investigations shall be conducted by the Applicant to reduce adverse effects to the characteristics of each property that contribute to its NRHP-eligibility. For sites eligible under Criterion d, significant data will be recovered through excavation and analysis. For properties eligible under Criteria a, b, or c, data recovery may include historical documentation, photography, collection of oral histories, architectural or engineering documentation, preparation of a scholarly work, or some form of public awareness or interpretation. Data gathered during the evaluation phase studies and the research design element of the Historic Properties Treatment Plan (HPTP) shall guide plans and data thresholds for data recovery; treatment will be based on the resource's research potential beyond that realized during resource recordation and evaluation studies. If data recovery is necessary, sampling for data-recovery excavations will follow standard statistical sampling methods, but sampling will be confined, as much as possible, to the direct impact area. Data-recovery methods, sample sizes, and procedures shall be detailed in the HPTP consistent with Mitigation Measure C-1c (Develop and implement Historic Properties Treatment Plan) and implemented by the Applicant only after approval by the BLM and CPUC. Following any field investigations required for data recovery, the Applicant shall document the field studies and findings, including an assessment of whether adequate data were recovered to reduce adverse project effects, in a brief field closure report. The field closure report shall be submitted to the BLM and CPUC for their review and approval, as well as to appropriate State repositories and local governments. Construction work within 100 feet of cultural resources that require data-recovery fieldwork shall not begin until authorized by the BLM or CPUC, as appropriate.

C-1f Train construction personnel. All construction personnel shall be trained regarding the recognition of possible buried cultural remains and protection of all cultural resources, including prehistoric and historic resources during construction, prior to the initiation of construction or ground-disturbing activities. The Applicant shall complete training for all construction personnel. Training shall inform all construction personnel of the procedures to be followed upon the discovery of archaeological materials, including Native American burials. Training shall inform all construction personnel that Environmentally Sensitive Areas (ESAs) must be avoided and that travel and construction activity must be confined to designated roads and areas. All personnel shall be instructed that unauthorized collection or disturbance of artifacts or other cultural materials on or off the right-of-way by the Applicant, his representatives, or employees will not be allowed. Violators will be subject to prosecution under the appropriate State and federal laws and violations will be grounds for removal from the project. Unauthorized resource collection or disturbance may constitute grounds for the issuance of a stop work order. The following issues shall be addressed in training or in preparation for construction:

Top Of PageGo To First Page