Word Document PDF Document |
ALJ/DMG/jyc Date of Issuance 6/25/2010
Decision 10-06-036 June 24, 2010
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking to Oversee the Resource Adequacy Program, Consider Program Refinements, and Establish Annual Local Procurement Obligations. |
Rulemaking 09-10-032 (Filed October 29, 2009) |
DECISION ADOPTING LOCAL PROCUREMENT OBLIGATIONS
FOR 2011 AND FURTHER REFINING THE RESOURCE
ADEQUACY PROGRAM
DECISION ADOPTING LOCAL PROCUREMENT OBLIGATIONS FOR 2011 AND FURTHER REFINING THE RESOURCE ADEQUACY PROGRAM 1
1. Summary 2
2. Procedural Background 2
3. Local RA for 2011 4
4. RA Program Modifications 19
4.1. Standard Capacity Product 19
4.2. Qualifying Capacity 24
4.2.1. Resource Classification Proposals 25
4.2.2. Counting Rules for Non-Dispatchable Resources
(QC Report - Section 10) 27
4.2.3. No Change to the Counting of Distribution Resources 29
4.2.4. Eliminate Forced Outages and Derates from Data to
Calculate QC and Possibly Include Resources Using
Historical Data in the SCP 31
4.2.5. Demand Response 35
4.3. Implementation Proposals 45
5. Comments on Proposed Decision 56
6. Assignment of Proceeding 57
Findings of Fact 57
Conclusions of Law 60
ORDER 62
Appendix A - Load-Serving Entities as Defined in Section 380(j)
Appendix B - Qualifying Capacity Methodology Manual
DECISION ADOPTING LOCAL PROCUREMENT OBLIGATIONS
FOR 2011 AND FURTHER REFINING THE RESOURCE
ADEQUACY PROGRAM
1. Summary
This decision establishes local capacity procurement obligations for
2011 applicable to Commission-jurisdictional electric load-serving entities. These procurement obligations are based on an annual study of local capacity requirements performed by the California Independent System Operator for 2011. For the first time in three years, the total local capacity requirements determined by the California Independent System Operator for all local areas combined increased slightly from the prior year; the increase is from
27,727 megawatts in 2010 to 28,058 megawatts in 2011.
In addition, this decision adopts several proposed resource adequacy (RA) program refinements. A Qualifying Capacity Methodology Manual is adopted to provide load-serving entities with clear direction for procuring RA resources. The penalty for failure to timely procure adequate capacity is modified. Finally, several issues are deferred to later portions of this proceeding, including a RA local true-up mechanism.